The Kitchen Project...
Weeks Six & Seven
Most of the time was spent taping, sanding and painting the walls for the cabinet installation... Cabinets were installed on Thursday and the template for the countertops happens next week. This weeks major thing will be the ceramic tile on the floor and installing the recessed lighting (as well as tying in all of the new electrical). Still hoping for substantial completion before Christmas.
Kitchen Remodel Weeks
Six and Seven 12/6/2008 |
| |
|
|
|
| |
|
|
|
| |